Order Now
Civil engineer CDR sample

Career Episode 2

INTRODUCTION

Time duration Jan 2009 to March 2009
Location Dubai, United Arab Emirates
Organization AWRostamani Building Industries
Project Al Fattan Towers
Position Technical Civil Engineer

[CE 2.1]

AWRostamani Building Industries was established in the year 1954, having more than 60 years of experience in Construction Industry with the full time working staff of 3800 and an operative work force of 4500+, The Company is spread into various divisions such as construction, Building Industries, property services, facilities management, Automobiles and money exchange.

BACKGROUND

[CE 2.2]

My employer was requested to design, fabricate and build the steel structure frame for the main signage of the building located on the roof level. The height of the building was 36.4m, the signage should resist the wind load would affect at this height, in addition to the self-weight and the aluminum weight considering the dynamic load may affect at this level as per the authority regulations.

Our company was requested to provide the full designed frame, authority approval and installation within three months as per the project schedule planed, in order to let the cladding company, proceed their work and finish the external façade.

Finishing the work in this quit short period was a challenge, in addition to the design challenge for a signage 7.2m height, 3.5 width and 20m length, to be erected on a free base area equal to 1.2 m width.

[CE 2.3]

Before casting the roof slab at the above-mentioned project, we were requested to provide the full details of the steel frame signage, the concrete pedestals details and anchorage base plate details in order to be inserted before the concrete casting. Therefore, my role started at this level, I visited the site and gathered all the information required for the building exposure category, studying the drawings, meeting the project manager and discuss all the issues were required to obtain the authority approval at the earliest.

[CE 2.4]

The Hierarchy of the project is shown below:

Civil Engineer CDR report

PERSONAL ENGINEERING ACTIVITY

[CE 2.5]

My Roles & Responsibilities

  • Liaising with the client engineer to investigate the affected area and concluding the best method to rectify that.
  • Preparing a probable estimate to complete the work
  • Conducting the traffic impact studies and proposing the best time to work in that area
  • Checking if any service interruptions are occurring during the construction phase of the project applying for the authority approvals and intimating the same to the Dubai police and media after the date is finalized to carry out the work
  • Mobilizing the resources, traffic diversions and executing the work
  • Coordinating with the testing team to take the samples for the work done and submitting it in the laboratory to carry out the required tests.
  • Conducting a joint survey to take the exact measurements for the work done
  • Guiding the draughtsman to prepare the as built drawing and submitting it to the client
  • By giving the inputs to the quantity surveyors to prepare the invoice and submitting it to the client

[CE 2.6]

After gathering all the inputs required to model & design the signage and based on the architectural and mechanical drawings, it was obvious for me that the free area to locate the columns is very limited and therefore the structure system should as cantilever frame not a tow hinged or tow fixed frame. Therefore, I started to model the signage using the Staad pro software, and applied the expected wind load pressure and suctions per the ASCE-05 stats.

Internal parameters should be defined and applied to achieve the accurate and realistic results. All though the cantilever frame was challenging to be economical and safe, I solved the issue of using big sections to resist the bid moments, by connecting these columns with back bracing worked as ties. These ties were supported with RCC columns terminated at the roof slab level.

Another issue faced in this project while designing was the displacements and deflection amounts at certain elements were exceeding the allowable as per the international codes. And therefore, I was requested to reduce these amounts to meet the code limits. And it was clear for me that deflection at end of the cantilever was higher due to own weight of the beams and bracing, and therefore, instead of adding bracing members, I decided to change the section of the bracing members with less in weight and more rigid section and that was the tube section instead of the angles. These modifications had developed the overall structure response and reduced the displacements and deflection values accordingly.

[CE 2.7]

My main role was to design a durable, safe and economic steel frame structure to perform as the main signage of the financial building, and this was including the design of the steel columns, girders, bracings and the connections between the members either bolted or welded connections. That’s in addition to the design of the concrete pedestal, by reflecting the structure max reactions to transfer them to the RCC columns, in check the demand-capacity ratio for these RCC columns to ensure that the loads transferred are within the allowable limits.

[CE 2.8]

I used AutoCAD, Staad pro V8i, ProkonV2.0 and Limcon software in this project. Being the civil structural engineer assigned for this job, I generated the takeoff quantity tool, and realized the exact weight required of each steel section considered as a part of the signage and prepared an estimation for the material cost considering the latest market steel prices to be part of the commercial offer were submitted to my line manager.

[CE 2.9]

I was coordinating the material delivery to site and installation as well therefore I was requested to initiate all the delivery notes and check the quality of the material delivered. And to handle the transaction process of the steel members by the tower crane from the store location to the roof level to proceed the installation, and this process required a huge coordination between us and the main contractor at site to include our request in the tower crane schedule, with the proper coordination with the project manager, the required materials and resources were provided without any failure.

[CE 2.10]

To deliver an economic, durable and safe steel structure frame was the main task and objective in this project. Therefore, I applied several techniques to achieve my goal, I reviewed the minimum loads design code ASCE-05 to figure out the live and wind load should be considered; therefore the realistic results been achieved. To utilize previous projects lessons to be learned also was very effective and helpful. I applied the theoretical technique while facing issues at site to run the problem inside the theoretical lube and ended up with the practical solution covering all the corresponds gabs might be found if a quick decision been taken.

[CE 2.11]

While designing the steel structure model, I developed an excel sheet calculating the wind load as per the cases defined in the ASCE code, considering the structure Hight, exposure type and the frame geometries. Also, while the execution, I developed an excel sheet reflecting the daily productivity at site, manpower, machines, materials, and losses. These daily reports were gathered to combine the weekly report should presented to my line manger to highlight any excess or delay may occur.

[CE 2.12]

Health and safety procedures were followed strictly to avoid any accident. Adequate briefing sessions were given to the labor before starting any activity, discussing the safety aspects to be taken care while carrying the work, brief discussion on the standard procedure to carry out the work (method statement).

As the working conditions were at the roof level, strict safety procedures were followed, specially while the welding process.

Water with extra added minerals were provided to the workers so that workers are kept hydrated all the times in extreme climatic conditions too.

[CE 2.13]

I was leading the estimation engineer, draught man, site supervisor and 5 technicians at site. I was successfully guiding them to ensure that all input information was correct and the generated outputs are accurate.

I used to meet my direct manager once a week, to brief him about the project status wither at the design stage or at the installation stage. Our discussion was based on the weekly report prepared including all the outstanding projects in the pipeline. I followed the recommendations received from my direct manager, especially which included any correspondence with the client or with the authority, to ensure that the company’s rights are reserved.

At the construction stage of this project, I use to join the project supervisor to check the daily productivity and the work done, and balanced. I was insisting to carry over all the site issues may appear and discuss them with my team to be resolved immediately.

It was required from me to combine the design report to be submitted to the authority showing the design criteria, inputs and outputs. That’s in addition to the weekly project report, which was including the projects details and status to be discussed along with my direct manager.

[CE 2.14]

SUMMARY

Project was successfully completed and delivered, we met the project schedule and quality planed, and even was able to provide a cost saving than the forecast estimation for about 15% savings. Therefore, we were able to achieve the project goals and objectives without any failure.

I utilized my engineering knowledge and background in this project at different aspects and stages. For example, at the design stage I was able to define the proper structure system of the signage based on the information gathered from the structural and architectural drawings received. Furthermore, I was able to predict the suitable steel section and connection details before designing them, and the design outputs doesn’t vary a lot from my prediction.

Learnings from the project are as below -

  • Accurate and economic design for the steel structures frames.
  • Carrying the installation of the steel frame on RC structures and the welding process at site.
  • Liaising with the authorities for the approvals
  • Studied the codes and their recommendation for the wind loads and allowable displacements.
  • Coordinating with the main contractor of the project to achieve the project program and ease the work process.

To read more.............. Kindly check the below links.

Top 10 Reasons to choose MyCDRHelp.com

We hold the apex position in providing services regarding CDR writing for engineers Australia. We are known to have very high success records for consistent team of professional writers having years of experience in the field of CDR preparation. We provide the best and trusted service for CDR writing and reviewing of all kinds of engineering disciplines. We provide services for career episode writing, plagiarism check and removal etc.

  • Each section of the CDR is presented in a coherent form, while taking in account the pre-eminent features.
  • The summary statement for the applied occupation is given special attention, as it is the most proficient aspect of the CDR.
  • Utmost emphasis is laid on the various sections of the CDR, from introduction to Summary, in order to ensure that every segment is presented precisely.
  • Preparation of CDR is done by a comprehensive evaluation of the projects in order to provide details to cater to the requirements by Engineers Australia for Australian immigration Competency Demonstration Report.
  • Technical jargons are avoided and each error is corrected as well as any inadequacy is taken care of within the required time duration for the CDR to be approved by EA.
  • Each section of the CDR is assessed as per the standards laid down by MSA (Migration Skill Assessment Booklet) in order to provide meticulous CDR.
  • MyCDRHelp.com ensures the client that they will be provided with the best quality CDR, that abides by the Australian immigration standards framed by Engineers Australia.
  • The qualified connoisseurs apply an analytical process so that the achievements of the clients are in accordance with their desired position and educational lineup.
  • Appropriate Australian English is used by the professional writers to write the content of the CDR to make it affluent.
  • It is made sure by the professionals of MyCDRHelp.com that CDR complies with the Australian standards and consists of the desired characteristics of the required profession of the client.

Should you need any further information, please do not hesitate to contact us.

[email protected]

Contact: +61-4-8885-8110

WhatsApp: +61-4-8885-8110

(Australia, USA, UK, UAE, Singapore, New Zealand)