[CE 2.1] I applied civil engineering skills in the project which has the below details:
Project Name: | PRS Lake Ville |
Duration: | June 2010 – December 2011 |
Location: | TRIVANDRUM, INDIA |
Organization: | ADS ASSOCIATES ENGINEERS & CONSULTANTS |
Position: | SITE ENGINEER |
[CE 2.2] PRS Lake Ville at Trivandrum, India is a multistory Apartment near Akullam Lake owned by the PRS group. A total of 2 years and 3 months was taken to complete the project. PRS Lake Ville is a luxury lakefront G+17 story building with 1 basement. ADS Associates was the main contractor for the project.
[CE 2.3] The project aim was the PRS Lake Ville which was based on carrying out the construction activities and implemented the pile tests for obtaining the necessary results linked with the design. I worked on the dynamic pile response PDA measurement and utilized the bar bending machine for carrying out the operation of steel bending.
[CE 2.4] The activities related to the project were conducted using civil engineering expertise and achieved the project scope with the usage of the technical concepts in the project. Various project objectives were attained and projects were split into sections for getting the maximum project results.
[CE 2.5] The flowchart:
[CE 2.6] I had these duties:
[CE 2.7] I was assigned to perform testing of piles in this project -
[CE 2.8]I did the calculation of the quantity of material, cost for performing jobs. I executed the bar bending schedule. I worked on the bills for subcontractors. I did the calculation of loads for pile testing. I also conducted the load settlement calculation and curve. I implemented the time load settlement curve. I obtained the value of ‘n’ in the standard penetration test. I used the excavators for excavating soil in the pile cap area. I used DMC piling machine for boring piles. I selected compactors for compacting the earth. I selected the concrete pumps for transferring the concrete to different areas. I selected the concrete transit mixer for carrying out the concrete from batching plant to site. I applied loader to load excavated earth to trucks. I implemented the PDA for the measurement of the dynamic pile response. I used the bar bending machine for bending the steel.
[CE 2.9]The main difficulty involved during the project was the excavation of the land for the pile cap. Since the land was nearby the backwater the water seepage was high during rainy days and high tide. During the time it was heavily raining since Kerala’s climate was mainly wet and maritime tropical seasonal downpours happen. Excavated area soil consisted of clayey silt / sandy silt and the stability of slope was very poor. Water seepage destabilized the slope. For dewatering the seepage water in the excavated area made the work delay every morning. As I had to find an economical solution and I referred to many journals. The piles on the land had steel casings up to ground level, which was cut till the top of the plain concrete level of the pile cap. These casings were sent as scraps from the project. I took permission from the project manager to use these scraps to protect the destabilized soil. The thickness of the casing was 10mm. I used these scrap casings and bent it with the help of the excavator to straighten like a sheet. I took the help of labors and excavators to insert the sheet into the soil. I placed the steel beams which were inserted in front of the sheet to support the sheet and soil.
[CE 2.10]I designed a dewatering system for the excavated area by excavating a pit and made a channel throughout the periphery of an excavated area with the help of labor sloping towards the excavated pit, so that the water will be the collected in the pit. I installed one 5 HP and one 3HP pumps to dewater and assigned one labor to check the whole system and water level in pit. By doing this design I saved a lot of time and work was more productive.
[CE 2.11]I got the chance to perform pile testing in my company before in other projects tests were given subcontract. Later, I was given training for engineers and staff in other projects. This in house testing saved huge money. By referring to the internet and journals, I got the knowledge and idea of doing pile load tests independently. I also managed the manpower and equipment from colleagues. The next main problem was the disposal of bentonite slurry. The bentonite used for DMC piling must be disposed of carefully and properly to avoid environmental issues. For this, management has given strict instructions to the subcontractor to carry and dispose of. They have contacted waste disposal agency and they cleared every week from bentonite slurry tank. I confirmed that it was not mixing with any drainage system or circulation with other water.
[CE 2.12]Safety was given high priority at the workplace. I made sure that the working at height was done while wearing a safety harness. I also addressed the environmental issue as the lake was near to the project, there were strict instructions from the management to protect the environment. I did not throw any waste into the backwaters. For that, I have given clear instructions to all the staffs and labors during site induction training. I attended weekly progress meetings with the deputy project manager. I reported to senior engineers and construction managers daily. I conducted the daily work based instructions and interactions with colleagues, supervisors, and foreman.
[CE 2.13] I prepared the daily and weekly reports about manpower and jobs were submitted to Construction Manager. I prepared soil investigation test reports based on SPT and CPT and collecting soil samples. I worked on the pile load test reports, graphs and pile bore logs using the technical civil engineering knowledge. There was a significant increment in my technical knowledge with the execution of this civil engineering project.
To read more.............. Kindly check the below links.
We hold the apex position in providing services regarding CDR writing for engineers Australia. We are known to have very high success records for consistent team of professional writers having years of experience in the field of CDR preparation. We provide the best and trusted service for CDR writing and reviewing of all kinds of engineering disciplines. We provide services for career episode writing, plagiarism check and removal etc.
Should you need any further information, please do not hesitate to contact us.
Contact: +61-4-8885-8110
WhatsApp: +61-4-8885-8110
(Australia, USA, UK, UAE, Singapore, New Zealand)