Order Now
EA Approved CDR Service

EA Approved CE 2 CDR Sample Architectural Engineer

Avail the best Architectural Engineering experts for CDR writing from MyCDRHelp.com to get 100% positive knowledge assessment from EA Australia. Please check CDR career episode 2 Sample

EA Approved CE 2 CDR Sample Architectural Engineer

Career Episode 2 on CDR Sample Architectural Engineer

Introduction

Time duration September 2016 to December 2016
Location Malaysia
Organization International Islamic University Malaysia
Project Structural Analysis & Design Office
Position

[CE 2.1]

This career episode relates to project titled “Structural Analysis & Design Office’’. The project was assigned to me as a part of my 4th Year 1st Semester of engineering at International Islamic University Malaysia.

Background

[CE 2.2]

I was required to prepare design report on the following beam, slab and staircases.

  • Calculation of all loads supported by the above beam, slab and staircase
  • Structural analysis using Moment Distribution Method (Allow for 20% moment redistribution)
  • Complete design calculation
  • Details drawings of the beam (longitudinal and cross sections)
  • Details drawing of the slab (plan and cross section)
  • Details drawings of the staircase (cross section)

[CE 2.4]

The project Hierarchy is given below -

Architectural Engineer CDR report

Personal Engineering Activity

[CE 2.5]

Constructon

Architectural Engineer CDR report
Office Ceramic tiles on in-situ reinforced solid slab. Suspended ceiling bellows beams. Lightweight partitions as required to offices.
Manager room Carpets on in-situ reinforced concrete solid slab. Suspended ceiling below beams
Corridor Ceramic tiles on in-situ reinforced concrete solid slab. Suspended ceiling below beams
Files room Cement render on in-situ reinforced concrete slab. No ceiling under.
Computer rooms Carpets on in-situ reinforced concrete solid slab. Suspended ceiling below beams
Staircase Ceramic tiles on in-situ reinforced concrete. Enclosed in 112.5mm x 3.0m height brickwork plastered on both sides.
Toilet Ceramic tiles on in-situ reinforced concrete slab. No ceiling under. All internal walling lightweight partition. Enclosed in 112.5mm x 3.0m height brickwork plastered on both sides.
External wall generally 112.5mm x 3.0m height brickwork plastered on both side.
Fire protection All elements of the construction to have minimum of 1 hour fire resistance.

[CE 2.6]

Calculations

I did following calculations

Dead Load, Gk:

Concrete Unit weight = 25 kN/m2

Brickwall unit weight = 2.6 kN/m2

Brickwall height = 3 m

Concrete render = 0.3 kN/m2

Ceramic tiles = 1 kN/m2

Lightweight partitions = 1 kN/m2

Building Services = 0.3 kN/m2

Ceiling = 0.5 kN/m2

Carpet = 0.05 kN/m2

Primary beam = 250 x 650 mm

Secondary beam = 250 x 500 mm

Slab thickness = 150 mm

Assumed Bars:

Ø bar 1 = 20 mm

Ø bar 2 = 16 mm

Ø link = 6 mm

Imposed Load, Qk

Office = 2.5 kN/m2

Corridor = 3.0 kN.m2

File Room = 5.0 kN/m2

Manager Room = 2.5 kN/m2M

Computer Room = 3.5 kN/m2

Dead Load & Imposed Load for each room:

Office:

Dead Load:

Slab self-weight = 25(0.15) = 3.75 kN/m2

Cement render = 0.30 kN/m2

Ceramic Tiles = 1.0 kN/m2

Lightweight partitions = 1.0 kN/m2

Building Services = 0.3 kN/m2

Ceiling = 0.5 kN/m2

Gk = 6.85 kN/m2

Imposed Load,

Qk = 2.5 kN/m2

[CE 2.7]

I also did calculations for Durability, Fire and Bond requirements

Min, cover with regard to bond cmin, b = 20 mm

Min, cover with regard to durability cmin, dur = 20 mm

Min required axis distance for R60 fire resistance,

asd = 30+10 = 40 mm

Min cover with regard to fire = Cmin = asd - ꬾlink -ꬾbar/2

= 40-6-20/2 = 24mm

Allowance in design for deviation, ∆Cdev = 10mm

Nominal cover, Cnom = Cmin + ∆Cdev = 24+10 = 34mm

[CE 2.8]

Distribution of actions from slabs to beams were as following -

Beam C/1-2

Ly/Lx = 5800/4200 = 1.38<2 (two-way slab)

Shear Coefficient βv =0.49

Slab Gk = 6.85 kN/m2 (office)

Slab Qk = 2.5 kN/m2 (office)

Beam self-weight = 25(0.65-0.15)x0.25=3.125 kN/m2

Brick weight = 2.6 x 3 = 7.8 kN/m2

Dead load from slab B1-C1/1-2: 2x(0.49)4.2x6.85 = 28.19 kN/m2

Gk = 28.19 + 3.125 + 7.8 = 39.11 kN/m

Imposed load from slab B1-C1/1-2

= 2x(0.49)4.2(2.5)=10.29kN/m2

Qk = 10.29 kN/m

Total Design load (W1)

W1 = 1.35 Gk + 1.5Qk

W1 = 1.35(39.11) +1.5(10.29) = 68.24 kN/m

Corridor

Slab Gk = 5.85 kN/m2

Slab Qk = 3 kN/m2

Load on beam C/2-3

Beam self-weight = 25(0.65-0.15) x 0.25=3.125 kN/m

Gk 3.125 = 3.125 kN/m2

Qk = 0 kN/m2

(Qk=0 because it is one-way and has no effects on beam C/2-3)

W2 = 1.35 (3.125) + 1.5(0)= 4.22 kN/m

I ignored the slab weight because it has no effects on the beam.

[CE 2.9]

I did Uniform load setup as following

Uniform load (W)

Architectural Engineer CDR report

Point load (P)

Architectural Engineer CDR report

[CE 2.10]

I did effective flange width as following

beff = ∑beff I + bw < b

beff I = 0.2bi + 0.1l0 < 0.2l0

Span C/1-2

bw = 250mm

hf = 150mm

h = 650mm

b1 = 1975 mm

b2 = 1975 mm

Actual flange width, b = b1 + b2 + bw = 1975+1975+250 = 4200mm

beff = ∑beff I + bw < b

beff I = 0.2bi + 0.1l0 < 0.2l0

l0 = 0.85l = 0.85 x 5800 = 4930 mm

beff 1 = 888 mm < 986 mm Use: 888 mm

beff 2 = 888 mm < 986 mm Use: 888mm

beff = 888 + 888 + 250 = 2026 mm < 4200mm

Span C/2-3

l0 = 0.7l = 0.7 x 3000 = 2100 mm

b1 = 1975 mm

b2 = 1975 mm

beff 1 = 605 mm > 420 mm Use: 420 mm

beff 2 = 605 mm > 420 mm Use: 420 mm

beff = 420 + 420 + 250 = 1090 mm < 4200mm

Span C/3-4

bw = 250mm

hf = 150mm

h = 650mm

b1 = 1975 mm

b2 = 4075 mm

Actual flange width, b = b1 + b2 + bw = 1975+4075+250 = 6300 mm

beff = ∑beff I + bw < b

beff I = 0.2bi + 0.1l0 < 0.2l0

l0 = 0.85l = 0.85 x 5800 = 4930 mm

beff 1 = 888 mm < 986 mm Use: 888 mm

beff 2 = 1308 mm > 986 mm Use: 986 mm

beff = 888 + 986 + 250 = 2124 mm < 6300 mm

[CE 2.11]

Main reinforcement was calculated as below

Span C/1-2

Effective depth (d) = h-Cnom - Ø link -1.5 Ø bar = 650-35-6-1.5x20 = 579 mm

Bending moment,

M = 216 KN.m

Mf = 0.565 Fck b hf (d-0.5hf) = 0.565 x 25 x 2026 x 150 x (579-0.5x150) = 2163.5 KN.m

M < Mf (Neutral axis is in the flange)

K = M /fckbd2 = 216x106 / (25x2026x5792) = 0.013

Z = d[0.5 + √(2& 0.25-k/(1.134 ) )] = 579 [0.5 + √(2& 0.25-0.013/(1.134 ) )] = 572.8 mm

As = M / 0.87Fyk Z = 216x106 /0.87x500 x 572.8

= 866 mm2

Minimum and Maximum reinforcement area:

As,min = 0.0013bd

0.0013bd = 0.0013x250x579 = 188.17 mm2

As,max = 0.04bh = 0.04x250x650 = 6500 mm2

[CE 2.12]

Slab Design

Assumptions

Ø bar = 10 mm

Concrete Unit weight = 25 kN/m2

Concrete render = 0.3 kN/m2

Materials:

Unit weight of concrete = 25 KN/m3

Characteristic strength of concrete, Fck = 25 KN/m2

Characteristic strength of steel, Fyk = 500 KN/m2

Primary beam = 250 x 650 mm

Secondary beam = 250 x 500 mm

Slab thickness = 150 mm

Slab thickness = 150 mm

Durability, Fire and Bond requirements

Min, cover with regard to bond cmin, b = 10 mm

Min, cover with regard to durability cmin, dur = 15 mm

Min required axis distance for R60 fire resistance,

a = 20 mm

Min cover with regard to fire = Cmin = a -0.5 Ø bar = 20-10/2 = 15 mm

Allowance in design for deviation, ∆Cdev = 10mm

Nominal cover, Cnom = Cmin + ∆Cdev = 15+10 = 25 mm

[CE 2.13]

I did shear force calculations as following

Two-way restrained slab

B1-C/1-2, C-C1/1-2, B1-C/3-4 (Office)

Long span Ly = 5800 mm

Short span Lx = 4200 mm

y / Lx = 1.4 < 2.0 (Two-way slab)

Case 2: One short edge discontinuous

Short Span:

Vsx1 = βsx1 nd Lx = (0.45) (13) (4.2) = 24.57 KN

Vsx2 = βsx2 nd Lx = (0.45) (13) (4.2) = 24.57 KN

Long Span:

Vsy1 = βsy1 nd Lx = (0.36) (13) (4.2)= 19.66 KN

Vsy2 = βsy2 nd Lx = (0.24) (13) (4.2) = 13.10KN

Design force VEd = 24.57 KN

Design shear resistance,

VRd,c = [0.12k(100 ρ 1Fck )1/3]bd

K = 1+ (200/d)1/2 < 2.0

K = 1+ (200/120)1/2 < 2.0

2.29>2.0 use 2.0

ρ 1 = As1/bd < 0.02

ρ 1 = 314/1000x120 < 0.02 = 0.003<0.02

VRd,c = [0.12x2(100 x0.003x25 )1/3]1000x120

= 56374 N = 56.4 KN

Vmin = [ 0.035K3/2 Fck1/2] bd

= 0.035 x 23/2 x 250.5 x 1000 x 120 = 59.4 KN

So, VRd,c = 56.4 KN > VEd

[CE 2.14]

Summary

I completed the project report efficiently and within the stipulated time. I did all the management of the project and calculated multiple aspects of the project very well. In case of any issues I always contacted my project supervisor. I also consulted internet resources and library for resolving the calculation issues.

FAQ

Frequently Asked Questions

Quick answers to common questions about our CDR services.

A Competency Demonstration Report (CDR) is a comprehensive technical document required by Engineers Australia (EA) to evaluate the engineering skills, knowledge, and competency of candidates migrating to Australia from countries whose degrees are not accredited under the Washington Accord.

An EA-approved CDR consists of three main elements: a list of Continuing Professional Development (CPD), three distinct Career Episodes (CEs) highlighting different engineering projects, and a cross-referenced Summary Statement mapping your work to EA competency elements.

Plagiarism is taken very seriously by Engineers Australia, who scan all submissions using advanced software (like Turnitin). To avoid rejection or a ban, write your report from scratch based on your real engineering experience. Our professional writers provide 100% unique, plagiarism-free reports.

Engineers Australia currently accepts IELTS, TOEFL iBT, and PTE Academic test scores. You must secure the minimum required scores (e.g., IELTS band 6 in each of the four modules) for a successful skills assessment.

Ready to Start Your Australia Migration Journey?

Get expert CDR, RPL, or KA02 report written by qualified engineering professionals. 7000+ engineers approved!

Need Instant Help? Connect with us: Email: contact@mycdrhelp.com Phone/WhatsApp: +61-4-8885-8110