Time duration | May 2015 to Jan 2016 |
Location | |
Organization | Universiti Teknologi PETRONAS (UTP) Perak, Malaysia |
Project | Design of Vinyl Chloride Monomer Production Plant |
Position | Engineering Student |
Project Supervisor | |
Project submitted to |
This career episode is about my project titled “Design of Vinyl Chloride Monomer Production Plant”. This project was carried out and submitted for Bachelor degree requirement in Petroleum Engineering in ________________________________________________ from ……………..to ………………
[CE 3.1]
The project was done during the graduate course in Petroleum Engineering in ____________________. The project was executed in congregation of 5 candidates under the supervision and advantageous guidance of Dr. Pradip Chnadra Mandal.
[CE 3.2]
Vinyl chloride is an organochloride with the formula H2C=CHCl that is also called vinyl chloride monomer, VCM. With an annual total production of 13 billion kilograms. VCM is among the top twenty largest petrochemicals (petroleum-derived chemicals) in world production. Normally, the need to find the process alternative that has the lowest cost is preferred, but it must be ensured that the process is safe, will satisfy environmental constraints, is easy to start up and operate, etc. The heuristics approach is applied, to eliminate certain process alternatives from further consideration, but it is necessary to design various alternatives and then to compare their cost. So, the goal of this project is to design an environmentally friendly, safe, and economically profitable vinyl chloride production plant.
[CE 3.3]
The purpose of this project was to fulfill the aptitude I have for Chemical Engineering. I joined the project as an additional member for the Academic Semester January 2016. The project supervisor was Dr. Pradip Chandra Mandal, whom I worked with for the two previous academic sessions. He welcomed the idea of me joining the group of Chemical Engineering Students, who are under his direct supervision, on their Plant Design Project course. However, I did not sit for any assessment throughout the project. I contributed where I could to my maximum capacity and learned a grasp of Chemical Engineering.
[CE 3.4]
This project work was completed in a flock of 5 students. I lead the team of engineers.
The Hierarchy of the project is displayed below:
[CE 3.5]
The main objective is to recommend the best possible design for VCM production and process. Besides, the objectives are to design green, sustainable and environment friendly process. It is decided that this plant will have a production capacity of 328 k-ton/year. Assuming the plant operates for 344 days, which means 21 days for maintenance work or unplanned shutdown occasion, it is calculated that the plant is to produce 636 mole of VCM per hour. The feedstocks are generally ethylene, chlorine gas, hydrochloric acid, and oxygen gas.
[CE 3.6]
I did the Project management of the system which invloved the modularization of the project in to definite number of stages & created a classification of the activities to be accomplished. I prearranged the entire project in two stages.
PHASE 1: During this phase I finalized the study of the conceptual as well as philosophical nitty-gritties of the proposed work & drew up an approach to achieve the desired goad.
PHASE 2: In this phase; I have employed strategies for successful execution. After execution I carried out the testing of the entire system.
[CE 3.7]
My Roles & Responsibilities were -
[CE 3.8]
Problem A
The first main issue I faced was on how to integrate the cold and hot streams in the plant in order to minimize the energy consumption significantly. Before adopting the heat integration process, the plant consumes 42.96 MW. Intensive research and follow-up with the supervisor were done in order to find the optimal solution to the issue.
Solution
Long after, Pinch technology was found to be the best way to optimize the energy consumption. The pinch technology requires understanding of the cold and hot areas where the integration could be matched. Six hot and cold streams identified as a whole. After that, composite curves, table algorithm and grand composite curve were constructed to analyze the heat recovery and to fully optimize the energy. Maximum Energy Recovery (MER) method is used to pair two or more streams which results in minimum heat utilization. Energy consumption after integration was 22.2 MW. The energy saving adopting the Pinch design method was up to 50 %.
[CE 3.9]
Problem B
The second issue was on how to simulate the process flow-sheeting as the simulation requires intensive knowledge of Aspen HYSYS simulation and how it functions. The team discussed the possible and practical approaches tackling the issue. The faculty has got many experts in HYSYS simulations so we sought assistance from the experts. The experts directed us to some references to read.
Solution
Intensive research was made so as to fully understand and apply the concepts. After two months, we gave a huge shot to run the simulation and interestingly it ran smoothly with no apparent issues. To confirm the simulation, we performed a manual calculation on mass and energy balance. The results from the manual mass and energy balance and the simulation were nearly even.
[CE 3.10]
Each member of the team was required to design one major equipment and one minor equipment. Oxy-chlorination reactor was set to be the major equipment to design. To produce VCM feedstock which is EDC, there are two ways either by direct chlorination or by oxy-chlorination process. The reactor that will be used to accumulate the oxy-chlorination process is packed bed reactors with shell and multiple contact tubes. The first step was to determine the operating temperature and pressure of the process which are 220 0C and 450 kPa respectively. The second step was to identify the appropriate volume and height. To determine the actual volume, manual calculations were involved. Moreover, Levenspiel plot (A graph of rate law versus conversion) was also adopted to find the volume which found to be 22.3 m3. The step after that was to calculate the number of tubes (2720 tubes) required by applying the equation (Nt = Actual Volume / Volume of one tube). Then, Shell inside diameter and Baffle diameter (5.007 m and 5.003 m respectively) were calculated using the below equations: Ds (Shell inside diameter) = 0. M + Bundle diameter D (Baffle Diameter) = Ds – 4.8 mm Since the reaction is exothermic, heat should be removed. The exothermic reaction can reach up to 500 oC. Heat Removal System was grounded.
[CE 3.11]
I performed the design calculation for oxy-chlorination reactor. The design calculations include finding the optimum volume to satisfy the desired output. The calculations were done manually and explained in detail in the report. Besides that, some data obtained from Aspen HYSYS simulation were used to calculate the reactor volume.
[CE 3.12]
The simulator I used in this project was Aspen HYSYS which used to simulate the VCM flow-sheeting process. Moreover, I used Hint software as a tool to minimize the energy consumption in the plant
[CE 3.13]
During this Project I gained extensive experience & knowledge of process simulation, debottlenecking & troubleshooting of different equipment. I also ameliorated my decision making & leadership skills. The project was efficaciously premeditated & I thoroughly verified the employability of project. This project elevated my project management, planning, analysis and implementation skills. The project was successfully completed and was highly admired by the Project Supervisor & head of the petroleum engineering department.
We hold the apex position in providing services regarding CDR writing for engineers Australia. We are known to have very high success records for consistent team of professional writers having years of experience in the field of CDR preparation. We provide the best and trusted service for CDR writing and reviewing of all kinds of engineering disciplines. We provide services for career episode writing, plagiarism check and removal etc.
Should you need any further information, please do not hesitate to contact us.
Contact: +61-4-8885-8110
WhatsApp: +61-4-8885-8110
(Australia, USA, UK, UAE, Singapore, New Zealand)